[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930341":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930341,601,2,"多选题","项目信息管理的主要内容包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","信息发现",false,{"key":16,"text":17,"correct":18},"B","信息收集",true,{"key":20,"text":21,"correct":18},"C","信息加工",{"key":23,"text":24,"correct":14},"D","信息审查",{"key":26,"text":27,"correct":18},"E","信息传递","BCE","",{"id":6,"name":31,"category":32,"favorite":33},"设备工程监理基础及相关知识","建筑工程",0]