[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930313":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930313,601,1,"单选题","按( )分类，设备工程进度计划可以分为年度进度计划、季度进度计划、月度进度计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划期",true,{"key":16,"text":17,"correct":18},"B","计划的范围",false,{"key":20,"text":21,"correct":18},"C","设备工程的工作过程",{"key":23,"text":24,"correct":18},"D","进度计划的表达方式","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]