[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930310,601,1,"单选题","下列关于应用生产能力指数法估算建设项目投资的说法中，正确的有( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","生产能力指数取值应考虑拟建项目与已建同类项目的投资来源差异",false,{"key":16,"text":17,"correct":14},"B","拟建项目与已建同类项目生产能力之比应限制在50倍以内",{"key":19,"text":20,"correct":21},"C","应考虑拟建项目与已建同类项目因建设时间不同而导致的价格水平差异",true,{"key":23,"text":24,"correct":14},"D","生产能力指数取值应限制在l～2之间","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]