[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930300,601,1,"单选题","按风险影响的范围不同，项目风险可分为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","纯风险和投机风险",false,{"key":16,"text":17,"correct":14},"B","独立风险和非独立风险",{"key":19,"text":20,"correct":21},"C","基本风险和特殊风险",true,{"key":23,"text":24,"correct":14},"D","可管理风险和不可管理风险","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]