[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930291":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930291,601,1,"单选题","项目总体计划是以项目( )计划为龙头的项目计划。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","范围",false,{"key":16,"text":17,"correct":14},"B","风险",{"key":19,"text":20,"correct":21},"C","总工期",true,{"key":23,"text":24,"correct":14},"D","总投资","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]