[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930278":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930278,601,1,"单选题","下列关于项目控制方法的说法，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","采用被动控制方法时，应首先收集实际数据",false,{"key":16,"text":17,"correct":14},"B","偏差分析是主动控制的基本步骤之一",{"key":19,"text":20,"correct":21},"C","主动控制可以预防偏差出现",true,{"key":23,"text":24,"correct":14},"D","前馈控制属于被动控制","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]