[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930268,601,1,"单选题","某工作最乐观估计时间为10天，最悲观估计时间为14天，最可能估计时间为12天，那么该工作持续时间为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":18},"B","12",true,{"key":20,"text":21,"correct":14},"C","13",{"key":23,"text":24,"correct":14},"D","14","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]