[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930254":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930254,601,1,"单选题","设备工程项目信息按照项目信息来源分类，可以分为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","投资控制信息、进度控制信息、质量控制信息和合同管理信息",false,{"key":16,"text":17,"correct":14},"B","静态信息和动态信息",{"key":19,"text":20,"correct":21},"C","项目内部信息和项目外部信息",true,{"key":23,"text":24,"correct":14},"D","设备设计过程信息、设备采购过程信息、设备制造过程信息、设备安装过程信息和没备调试过程信息","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]