[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930240,601,1,"单选题","设备的规划、设计、采购、制造、安装、调试等设备形成的全过程和\u002F或最终形成的结果，我们统称为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设备监理",false,{"key":16,"text":17,"correct":14},"B","设备工程项目",{"key":19,"text":20,"correct":21},"C","设备工程",true,{"key":23,"text":24,"correct":14},"D","设备形成过程","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]