[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930231":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930231,601,1,"单选题","有关单位编制设备工程进度计划必须以( )为首要限制条件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","约束条件",false,{"key":16,"text":17,"correct":14},"B","风险分析资料",{"key":19,"text":20,"correct":21},"C","合同文件及相关文件",true,{"key":23,"text":24,"correct":14},"D","设备工程所在地的环境及所需资源状况","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]