[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930205,601,1,"单选题","项目风险管理过程包括制定、( )和管理风险处理方案等过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监督",false,{"key":16,"text":17,"correct":18},"B","选择",true,{"key":20,"text":21,"correct":14},"C","指导",{"key":23,"text":24,"correct":14},"D","控制","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]