[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},930202,601,1,"单选题","确定设备工程各工作前后顺序的依据包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织逻辑",false,{"key":16,"text":17,"correct":18},"B","有关工艺及组织方面的约束条件",true,{"key":20,"text":21,"correct":14},"C","工艺逻辑",{"key":23,"text":24,"correct":14},"D","合同及其他相关文件","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]