[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930188":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930188,601,1,"单选题","关于设备监理与项目承包商的项目管理之间的关系，表述不正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备监理单位与承包商之间是合同关系，必须接受监理单位的监督",true,{"key":16,"text":17,"correct":18},"B","设备监理单位与承包商之间是监理与被监理的关系",false,{"key":20,"text":21,"correct":18},"C","设备监理工程师根据监理合同的约定，对承包商的履约行为进行监督和管理",{"key":23,"text":24,"correct":18},"D","设备监理单位还要坚持公正立场，不损害承包商的正当权益","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]