[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930164":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930164,601,1,"单选题","下列各组被监理单位用表与监理单位用表中，不存在对应关系的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","方案报审表--方案审批表",true,{"key":16,"text":17,"correct":18},"B","索赔申请表--索赔审核表",false,{"key":20,"text":21,"correct":18},"C","进度计划报审请表--进度计划审批表",{"key":23,"text":24,"correct":18},"D","监理工程师通知单--监理工程师通知回复单。","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]