[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930085":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930085,601,1,"单选题","某建设工程由甲.乙.丙.丁4个单位工程组成，甲单位工程最先开工：甲单位工程开工后1个月乙单位工程开工；甲单位工程开工后2个月丙.丁单位工程同时开工。则该建设工程开工报审表的正确填报方式是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","甲.乙2个单位工程分别填报，丙.丁2个单位工程统一填报",true,{"key":16,"text":17,"correct":18},"B","甲单位工程单独填报，乙.丙.丁3个单位工程统一填报",false,{"key":20,"text":21,"correct":18},"C","甲.乙2个甲位工程统一填报，丙.丁2个单位工程统一填报",{"key":23,"text":24,"correct":18},"D","甲.乙.丙.丁4个单位工程统一填报","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]