[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930076,601,1,"单选题","在项目管理过程中，编制资源计划属于.( )的子过程。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目集成管理",false,{"key":16,"text":17,"correct":14},"B","项目范围管理",{"key":19,"text":20,"correct":14},"C","项目时间管理",{"key":22,"text":23,"correct":24},"D","项目费用管理",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]