[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930073":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930073,601,1,"单选题","项目时间管理的各个子过程中，在制订项目进度计划前进行的工作不包括( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","排列活动顺序",false,{"key":16,"text":17,"correct":14},"B","估算活动持续时间",{"key":19,"text":20,"correct":14},"C","估算活动资源",{"key":22,"text":23,"correct":24},"D","控制进度",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]