[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},930064,601,1,"单选题","某工作，其最乐观估计持续时间为6天，最可能估计持续时间为9天，最悲观估计持续时间为18天，则该工作期望持续时间为( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":14},"B","9",{"key":19,"text":20,"correct":21},"C","10",true,{"key":23,"text":24,"correct":14},"D","11","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]