[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930052":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930052,601,1,"单选题","设备工程中的安装工程直接费由直接工程费和( )组成。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施费",true,{"key":16,"text":17,"correct":18},"B","规费",false,{"key":20,"text":21,"correct":18},"C","企业管理费",{"key":23,"text":24,"correct":18},"D","业主管理费","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]