[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930018":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},930018,601,1,"单选题","项目风险影响是指风险发生对项目目标实现造成的影响，按我国设备工程管理的惯例，下列有关设备工程风险影响的表述，错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管理水平改善",true,{"key":16,"text":17,"correct":18},"B","时间进度延误",false,{"key":20,"text":21,"correct":18},"C","工程费用超支",{"key":23,"text":24,"correct":18},"D","工程质量事故","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]