[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930004":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},930004,601,1,"单选题","设备工程进度计划依据( )的不同，可划分为设计进度计划、采购进度计划、设备制造进度计划、设备储运进度计划和安装调试进度计划。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划期",false,{"key":16,"text":17,"correct":14},"B","表达方式",{"key":19,"text":20,"correct":14},"C","专业类型",{"key":22,"text":23,"correct":24},"D","工作过程",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]