[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},929990,601,1,"单选题","承包商与分包商的冲突，原则上应该由( )负责协调解决。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","业主",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":14},"C","设备监理工程师",{"key":22,"text":23,"correct":24},"D","承包商的项目经理",true,"",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]