[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},929962,601,1,"单选题","在设备工程项目实施过程中，对被监理方提交的方案、计划和各种申请或报告，监理方应及时进行检查、验证，并将意见或建议以( )形式反馈。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","电话",false,{"key":16,"text":17,"correct":14},"B","口头",{"key":19,"text":20,"correct":21},"C","书面",true,{"key":23,"text":24,"correct":14},"D","会议","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]