[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},929911,601,1,"单选题","在设备工程进度计划体系中，设备工程进度计划按计划的范围分类，可划分为前期工作进度计划、总进度计划、( )等。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备储运进度计划",false,{"key":16,"text":17,"correct":18},"B","分系统进度计划",true,{"key":20,"text":21,"correct":14},"C","季度进度计划",{"key":23,"text":24,"correct":14},"D","横道图计划","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]