[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929902":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},929902,601,1,"单选题","如果设备制造交货期需延期，被监理单位应用( )，并详细说明原因和延期的计划。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","延期申请表",false,{"key":16,"text":17,"correct":18},"B","进度计划报审表",true,{"key":20,"text":21,"correct":14},"C","临时延期申请表",{"key":23,"text":24,"correct":14},"D","施工组织设计报审表","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]