[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929893":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},929893,601,1,"单选题","设备采购工作程序包括编制采购计划、确定合格供货厂商、报价评审及签订合同、( )、催交、包装和运输等环节。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","明确该设备质量要求和目标",false,{"key":16,"text":17,"correct":14},"B","明确该设备的接收准则",{"key":19,"text":20,"correct":21},"C","调整采购进度计划",true,{"key":23,"text":24,"correct":14},"D","适应新产品开发要求","",{"id":6,"name":27,"category":28,"favorite":29},"设备工程监理基础及相关知识","建筑工程",0]