[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929828":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},929828,600,1,"单选题","某高速公路一座特大桥要跨越一条天然河道。试问，下列可供选择的桥位方案中，何项方案最为经济合理？（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","河道宽而浅，但有两个河汊",false,{"key":16,"text":17,"correct":14},"B","河道正处于急湾上",{"key":19,"text":20,"correct":21},"C","河道窄而深，且两岸岩石露头较多",true,{"key":23,"text":24,"correct":14},"D","河流一侧有泥石流汇入","根据《公路桥涵设计通用规范》（JTG D60—2004）第3.1.1条规定，特大桥、大桥桥位应选择在河道顺直稳定段，河床地质良好、河槽能通过大部分设计流量的河段，不宜选择在河汊、沙洲、古河道、急湾、汇合口、港口作业区及易形成流冰、流木阻塞的河段以及断层、岩溶、滑坡、泥石流等不良地质的河段，因为河道顺直稳定段，桥位较为稳定，桥长较短，调治构造物少，工程较省；急弯处，洪水容易冲刷河岸，桥头不稳，防护和调治工程量大，养护维修费用高；侧向有泥石流汇入的河段地形复杂，水流紊乱，甚至桥孔易被堵塞，对桥梁安全不利。故C项方案较其他选项最为有利。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业考试一级","建筑工程",0]