[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-929149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},929149,600,1,"单选题","有吊车的单层单跨砖砌体排架厂房，已知H=8.5m，Hu=3.0m，Iu=0.88×1010mm4，Il=4.806×1010mm4，设为刚弹性方案房屋。当荷载组合不考虑吊车作用时，变截面柱上段计算高度Hu0和变截面柱下段计算高度Hl0为下列何组数值？（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","排架方向：Hu0=6m，Hl0=10.2m",true,{"key":16,"text":17,"correct":18},"B","排架方向：Hu0=7.5m，Hl0=12.75m",false,{"key":20,"text":21,"correct":18},"C","排架方向：Hu0=6m，Hl0=12.7m",{"key":23,"text":24,"correct":18},"D","排架方向：Hu0=6m，Hl0=8.22m","根据《砌体结构设计规范》（GB 50003—2011）第5.1.4条和第5.1.3条表5.1.3可知，对有吊车厂房，当荷载组合不考虑吊车作用时，变截柱上段的计算高度为： 排架方向，Hu0=2.0×Hu=2.0×3.0=6.0m； 垂直排架方向，Hu0=1.25Hu=1.25×3.0=3.75m； 变截柱下段的计算高度可按下列规定采用：1\u002F3＜Hu\u002FH=3.0\u002F8.5=0.353＜1\u002F2，故修正系数为：μ=1.3-0.3Iu\u002FIl=1.3-0.3×（0.88\u002F4.806）=1.245； 排架方向：Hl0=1.2Hμ=1.2×8.5×1.245=12.7m； 垂直排架方向：Hl0=1.0Hμ=1.245×8.5=10.58m。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业考试一级","建筑工程",0]