[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-928974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},928974,600,1,"单选题","有吊车的单层单跨砖砌体排架厂房，已知H=8.5m，Hu=3.0m，Iu=0.88×10^10mm4，Il=4.806×10^10mm4，设为刚弹性方案房屋。当荷载组合不考虑吊车作用时，变截面柱上段计算高度Hu0和变截面柱下段计算高度Hl0为下列何组数值 ( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","排架方向：Hu0=6m，Hl0=10.2m 垂直排架方向：Hu0=3.75m，Hl0=8.5m",false,{"key":16,"text":17,"correct":14},"B","排架方向：Hu0=7.5m，Hl0=12.75m 垂直排架方向：Hu0=3.75m，Hl0=8.5m",{"key":19,"text":20,"correct":21},"C","排架方向：Hu0=6m，Hl0=12.7m 垂直排架方向：Hu0=3.75m，Hl0=10.58m",true,{"key":23,"text":24,"correct":14},"D","排架方向：Hu0=6m，Hl0=8.22m 垂直排架方向：Hu0=3.75m，Hl0=6.85m","",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业考试一级","建筑工程",0]