[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927674":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927674,598,1,"单选题","预压固结的地基处理工程中，对缩短工期更有效的措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设置水平向排水砂层",true,{"key":16,"text":17,"correct":18},"B","加大地面预压荷载",false,{"key":20,"text":21,"correct":18},"C","减小地面预压荷载",{"key":23,"text":24,"correct":18},"D","用高能量机械压实","在软粘土地基中，设置一系列砂井，在砂井之上铺设砂垫层或砂沟，砂井口径越小，固结的越快。人为地增加土层固结排水通道，缩短排水距离，从而加速固结，并加速强度增长。设置水平向排水砂层和用高能量机械压实，都能够加速固结，缩短工期，但影响固结的主要因素是水分，设置水平向排水砂层，缩短工期的效果更显著。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]