[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927526":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927526,598,1,"单选题","一多层框架结构，主体结构验收后停建四年，继续施工时使用单位提出增加一层，需实测梁、柱混凝土强度，应采用的检测方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","钻芯法",true,{"key":16,"text":17,"correct":18},"B","超声法",false,{"key":20,"text":21,"correct":18},"C","超声—回弹综合法",{"key":23,"text":24,"correct":18},"D","回弹法","由于主体结构停建时间长，又要增加一层，可用钻芯法取圆柱体试件进行抗压强度测试，可直接作为混凝土强度的换算值。用超声法、超声—回弹综合法和回弹法来推定混凝土的强度，只可作为结构混凝土强度的参考值。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]