[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927515":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},927515,598,1,"单选题","关于伪静力试验需要观测的项目，下列各项不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","力和位移或应变",false,{"key":16,"text":17,"correct":14},"B","弯矩和曲率",{"key":19,"text":20,"correct":14},"C","剪力和剪切变形、扭矩和扭转角",{"key":22,"text":23,"correct":24},"D","荷载设计值",true,"低周反复静力加载试验又称为伪静力或拟静力试验。试验观测项目主要有：①荷载—变形曲线；②梁或柱端位移；③构件塑性铰区段曲率或转角；④节点核心区剪切角；⑤梁柱纵筋应力；⑥核心区箍筋应力；⑦梁内纵筋通过核心区的滑移量Δ。D项，荷载设计值不是观测得到的，是由结构本身的性质及外部条件共同确定的。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]