[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927506,598,1,"单选题","当仅用3个位移计对简支梁均布荷载下进行最大挠度测量时，这3个位移计的位置应该在（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一个在支座，两个在跨中",false,{"key":16,"text":17,"correct":18},"B","一个在跨中，两个在两个支座处",true,{"key":20,"text":21,"correct":14},"C","一个在跨中，两个在梁的两个端头",{"key":23,"text":24,"correct":14},"D","一个在跨中，一个在支座处，一个在梁的另一端头","受弯构件最重要的就是测定跨中最大挠度及梁的弹性挠度曲线。为了获得梁的实际挠度值，试验时必须考虑支座沉陷的影响。如果跨中的挠度是相对于地面测定，在试验时两个端点处支座会产生沉陷，因此，在两端点必须布置测点。跨中是最大挠度的地方必须要布置一个测点，所以最少要布置三个测点。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]