[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927161":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},927161,598,1,"单选题","在计算由温差引起的预应力混凝土构件预应力损失σ13时，温差Δt指的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","钢筋与混凝土之间的温差",false,{"key":16,"text":17,"correct":14},"B","钢筋与混凝土产生粘结力后，钢筋与承拉设备之间的温差",{"key":19,"text":20,"correct":14},"C","张拉钢筋时，钢筋与承拉设备之间的温差",{"key":22,"text":23,"correct":24},"D","混凝土蒸汽养护时，钢筋与承拉设备之间的温差",true,"根据《混凝土结构设计规范》（GB 50010—2010）第10.2.1条的规定，在计算由温差引起的预应力混凝土构件预应力损失σ13时，温差Δt指的是加热养护时，钢筋与承拉设备之间的温差。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]