[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927117":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927117,598,1,"单选题","对工程网络进行“资源有限，工期最短”的优化的主要目的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","尽可能缩短工期，满足资源限量",false,{"key":16,"text":17,"correct":18},"B","延长工期最短，满足资源限量",true,{"key":20,"text":21,"correct":14},"C","尽可能缩短工期，使得资源消耗量最低",{"key":23,"text":24,"correct":14},"D","延长工期最短，使得资源消耗量最低","网络优化是指在既定条件下，按照某一衡量指标（工期、资源、成本），利用时差调整来不断改善网络计划的最初方案，寻求最优方案的过程。“资源有限，工期最短”是指通过调整计划安排，在满足资源限制的条件下，使工期延长幅度达到最小。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]