[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927103":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927103,598,1,"单选题","钢筋绑扎接头时，受压钢筋绑扎接头搭接长度是受拉钢筋绑扎接头搭接长度的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5倍",false,{"key":16,"text":17,"correct":18},"B","0.7倍",true,{"key":20,"text":21,"correct":14},"C","1倍",{"key":23,"text":24,"correct":14},"D","1.2倍","为了使绑扎钢筋有更好的持久性，且不易拉开或压分开，钢筋绑扎接头时，受压钢筋绑扎接头搭接长度是受拉钢筋绑扎接头搭接长度的0.7倍。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]