[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927102":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927102,598,1,"单选题","在网络计划中，若某工序的总时差为5d，局部时差（自由时差）为3d，则在不影响后续工作最早开始时间的前提下，该工序所具有的最大机动时间为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2d",false,{"key":16,"text":17,"correct":18},"B","3d",true,{"key":20,"text":21,"correct":14},"C","5d",{"key":23,"text":24,"correct":14},"D","8d","总时差是指在不影响工期的前提下，一项工作可以利用的机动时间。自由时差是指在不影响其紧后工作最早开始时间的前提下，一项工作可以利用的机动时间。所以最大机动时间即为局部时差为3d。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]