[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927093":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},927093,598,1,"单选题","进行资源有限—工期最短优化时，当将某工作移出超过限量的资源时段后，计算发现工期增量小于零，以下说明正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总工期会延长",false,{"key":16,"text":17,"correct":14},"B","总工期会缩短",{"key":19,"text":20,"correct":14},"C","总工期不变",{"key":22,"text":23,"correct":24},"D","这种情况不会出现",true,"“资源有限，工期最短”优化是指利用网络的自由时差和总时差来优化资源的方法。未超出原工期时，总工期不变；超出原工期时，有工期增量。所以工期增量小于零的情况不会出现。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]