[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927082,598,1,"单选题","竣工验收的组织者是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","质检单位","建设项目经过施工，全部或部分可以正式交付使用时，先由施工企业自验后提出《验收交接申请报告》（竣工报告），项目的建设单位或上级主管部门根据报告在一定时期内组织竣工验收工作。视验收需要，要有建设单位、设计单位、施工单位，质检单位、环保、消防、卫生防疫等单位人员参加。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]