[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927079":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927079,598,1,"单选题","质量管理需按PDCA循环组织质量管理的全部活动，其中的D是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划",false,{"key":16,"text":17,"correct":18},"B","实施",true,{"key":20,"text":21,"correct":14},"C","检查",{"key":23,"text":24,"correct":14},"D","行动","PDCA循环是“计划（Plan）→实施（Do）→检查（Check）→总结（Action）”工作循环的简称。它是企业推行全面质量管理（TQC）在方法上的重大变革。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]