[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927076":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927076,598,1,"单选题","图为某工程双代号网络图，工作①—③的局部时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","从图中可以看出工作①—③的紧后工作为③—④，而工作③—④的最早开始时间为其紧前工作①—③和②—③的最大值，即4+3=7（天）。局部时差=紧后工作的最早开始时间-本工作的最早完成时间，则工作①—③的局部时差为：4+3-5＝2（天）。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]