[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927074":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},927074,598,1,"单选题","某流水施工组织成加快加倍节拍流水，施工段数为6，甲、乙、丙三个施工过程的流水节拍分别为6、4和2d，其流水工期为（ ）d。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","22",true,{"key":23,"text":24,"correct":14},"D","16","流水步距Kb=最大公约数 专业工作队数目：bⅠ=6\u002F2=3（个），bⅡ=4\u002F2=2（个），bⅢ=2\u002F2=1（个），n1=bⅠ+bⅡ+bⅢ=3+2+1=6（个），施工段数m=n1=6（段），所以总工期T=（6+6-1）×2=22d。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]