[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927071":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},927071,598,1,"单选题","在固定节拍专业流水中，为缩短工期，两个相邻的施工过程应当（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","保持一定间距",false,{"key":16,"text":17,"correct":14},"B","保持固定间距",{"key":19,"text":20,"correct":21},"C","尽量靠近",true,{"key":23,"text":24,"correct":14},"D","保证连续性","固定节拍流水施工是一种最理想的流水施工方式，其特点如下：①所有施工过程在各个施工段上的流水节拍均相等；②相邻施工过程的流水步距相等，且等于流水节拍； ③专业工作队数等于施工过程数，即每一个施工过程成立一个专业工作队，由该队完成相应施工过程所有施工段上的任务；④各个专业工作队在各施工段上能够连续作业，施工段之间没有空闲时间。为了缩短工期，两个相邻的施工过程应当尽量靠近。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]