[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927069":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},927069,598,1,"单选题","某项工作有两项紧后工作D和 E，D的最迟完成时间为20d，持续时间为13d；E最迟完成时间为15d，持续时间为10d。则本工作的最迟完成为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20d",false,{"key":16,"text":17,"correct":14},"B","15d",{"key":19,"text":20,"correct":14},"C","10d",{"key":22,"text":23,"correct":24},"D","5d",true,"本工作的最迟完成时间为各紧后工作最迟开始时间中取最小值，经计算得：D的最迟开始时间=D的最迟完成时间-D的持续时间，即20-13=7d，D、E的最迟开始时间为15-10=5d。所以，本工作的最迟完成时间为5d。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]