[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927068,598,1,"单选题","对整个建设项目的施工进行通盘规划，带有全局性的技术经济文件是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织总设计",true,{"key":16,"text":17,"correct":18},"B","施工组织条件设计",false,{"key":20,"text":21,"correct":18},"C","单位工程施工设计",{"key":23,"text":24,"correct":18},"D","分部工程施工设计","施工组织总设计是以整个建设项目或民用建筑群为对象编制的，是对整个建设工程的施工过程和施工活动进行全面规划，统筹安排，以确定建设总工期、各单位工程开展的顺序及工期、主要工程的施工方案、各种物资的供需计划、全工地性暂设工程及准备工作、施工现场的布置和编制年度施工计划。因此，施工组织总设计是总的战略部署，是指导全局性的技术经济纲要。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]