[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927067":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},927067,598,1,"单选题","外墙抹灰的产量定额为4m2\u002F工日，则相应的时间定额为（ ）工日\u002Fm2。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.25",true,{"key":16,"text":17,"correct":18},"B","0.5",false,{"key":20,"text":21,"correct":18},"C","1",{"key":23,"text":24,"correct":18},"D","2","时间定额与产量定额互为倒数。故产量定额为4m2\u002F工日时，其相应的时间定额为0.25工日\u002Fm2。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]