[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927065":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},927065,598,1,"单选题","在确定施工过程的先后顺序时，应考虑（ ）。 （1）施工工艺的要求；（2）施工人员的素质；（3）安全技术的要求；（4）施工质量的要求；（5）施工组织的要求；（6）施工成本的要求。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","（1）（2）（3）（4）（5）",false,{"key":16,"text":17,"correct":14},"B","（1）（2）（3）（4）（6）",{"key":19,"text":20,"correct":21},"C","（1）（3）（4）（5）",true,{"key":23,"text":24,"correct":14},"D","（1）（3）（4）（5）（6）","在确定施工过程的先后顺序时，应考虑：①施工工艺的要求；②施工方法和施工机械的要求；③施工组织的要求；④施工质量的要求；⑤当地的气候要求；⑥安全技术的要求。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]