[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},927063,598,1,"单选题","下列关于施工组织总设计的描述，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工组织总设计是在初步设计和扩大初步设计批准后进行编制的",false,{"key":16,"text":17,"correct":18},"B","施工组织总设计是由总承包单位的总工程师负责编制的",true,{"key":20,"text":21,"correct":14},"C","施工组织总设计是施工单位编制施工计划和单位工程施工组织设计的依据",{"key":23,"text":24,"correct":14},"D","施工组织总设计是指导施工全过程各项活动的技术、经济的综合性文件","施工组织总设计是以一个建设项目或建筑群为编制对象，用以指导其施工全过程各项活动的技术、经济的综合性文件。它是在初步设计或扩大初步设计批准后，由总承包单位的总工程师负责，会同建设、设计和其他分包单位的工程师共同编制的。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]