[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927057":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},927057,598,1,"单选题","当柱平卧起吊的抗弯能力不足时，吊装前需先将柱翻身后再绑扎起吊，此时应采用的绑扎方法是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","旋转绑扎法",false,{"key":16,"text":17,"correct":14},"B","两点绑扎法",{"key":19,"text":20,"correct":21},"C","直吊绑扎法",true,{"key":23,"text":24,"correct":14},"D","斜吊绑扎法","根据起吊后柱身是否垂直，可分为斜吊法和直吊法，相应的绑扎方法有斜吊绑扎法和直吊绑扎法。当柱平卧起吊的抗弯强度满足要求时，可采用斜吊绑扎法；当柱平卧起吊的抗弯强度不足时，吊装前需先将柱翻身后再绑扎起吊，此时应采用直吊绑扎法；当柱较长、需采用两点起吊时，也可采用两点斜吊和直吊绑扎法。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]