[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-927053":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},927053,598,1,"单选题","为保证施工质量，后张法工艺中孔道留设施工应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在混凝土浇筑后尽快抽管",false,{"key":16,"text":17,"correct":14},"B","初凝前抽管",{"key":19,"text":20,"correct":21},"C","初凝后、终凝前抽管",true,{"key":23,"text":24,"correct":14},"D","尽量不抽管","后张法孔道留设的方法有三种：①钢管抽芯法，适用于直线管道；②胶管抽芯法，可用于直线，曲线或折线孔道；③预埋管法。为保证施工质量，后张法工艺中孔道留设施工应在初凝后、终凝前抽管。",{"id":6,"name":27,"category":28,"favorite":29},"(结构) 专业基础考试一级","建筑工程",0]